No.

Charter/Standard

 
1. Application for Engineering plans involving Drain and Road Plans,Street lighting Plan,Earthworks Plan and Sanitary Plan will be decided within a period not exceeding fifty(50) days provided all documents submitted are complete and in order as well as in compliance with all the Council’s conditions.
2. Recommendation for Occupation Certificate will be made within ten(10) working days.
3. Approval for Road Digging Permit will be issued within seven(7) days subject to compliance with all the Department’s conditions.
4. Technical comments/opinion willl be submitted within twenty five(25) days.
5. Payment voucher will be prepared and submitted to the Treasury Department within seven (7) days from date of receipt of invoice.
6. Action on complaints received will be taken within two (2) working days and reply will be given within three (3) working days from the date of receipt of the complaint.